1 |
Rectifier Existing or Re-Use |
| 2.3.1.2 |
2 |
Rectifier Brand and Type |
| 2.3.1.3 |
3 |
Rectifier Module Quantity |
| 2.3.1.4 |
4 |
Rectifier Load |
| 2.3.1.5 |
5 |
ACPDB Condition (cable, mcb, arrester, grounding connections) |
| 2.3.1.6 |
6 |
COS Box condition open and close |
|
7 |
Number of Genset installed |
| 2.3.1.8 |
8 |
Grounding to Neutral Voltage less than 5 V |
| 2.3.1.9 |
9 |
Seal and condition of KWH Meter |
| 2.3.1.10 |
10 |
Rectifier installed properly as Design Pack, BOQ and Site Model |
| 2.3.1.11 |
11 |
ZTE SCU or Huawei Neteco for NMS Power Monitoring installed properly as site model |
| 2.3.1.12 |
12 |
NMS Power Monitoring is properly connected and can be monitored (all alarm visible) |
| 2.3.1.13 |
13 |
All Rectifier Alarm cleared |
|
14 |
Rectifier Parameter Setting as standard from planing |
| 2.3.1.14.1 |
|
Fload Voltage |
| 2.3.1.14.2 |
|
Equal Voltage |
| 2.3.1.14.3 |
|
Out. High Off |
| 2.3.1.14.4 |
|
DC Under Voltage |
| 2.3.1.14.5 |
|
Batery Low Voltage |
| 2.3.1.14.6 |
|
Charge Currant Limit |
| 2.3.1.14.7 |
|
Automatic Equal Charge |
| 2.3.1.14.8 |
|
End Voltage Test |
| 2.3.1.14.9 |
|
LLVD 1 Value |
| 2.3.1.14.10 |
|
BLVD 1 Value |
| 2.3.1.14.11 |
|
Battery Temp COmpensation |
|
15 |
LLVD1 and LLVD2 (BLVD) Connection as standard from planning |
| 2.3.1.15.1 |
|
LLVD1 Connection to RRU as table below |
| 2.3.1.15.2 |
|
LLVD2 (BLVD) Connection to BBU, MW, IPRAN, HTISCC800, ZTE SCU, Colling System as table below |
Maksimal 10 foto. Format JPG/PNG.